Magnolia-Plaza Reliability Project
Tequesquite Landfill Solar Project
4kV – 12kV Voltage Conversions (some pole replacements)
Where: Brockton Arcade: Brockton, Arlington, Yellowstone, Nelson, DeAnza, Glacier
Start: 6/18/2018
End: 8/31/2019
Cable Rejuvenation
Where: Canyon Crest Area
- Upgrading the electrical system to increase reliability and efficiency
- RPU Contractor crew treating existing cables and installing electric substructures.
- Working hours are from 8:30 am to 3:30 pm, Monday through Friday.
- Cable Rejuvenation Map - Area 3 & 4
Start: 10/21/2019
End: 1/10/2020
Air Resources Board Building Development Work
Where: Iowa Avenue between University and Martin Luther King:
- Street widening (Public Works) and utility undergrounding work will be start in late spring.
- Working hours for building construction are from 8:30am to 3:00 pm – Monday through Friday.
- Part of Iowa will be shut down during those hours with a detour in place intermittently as work continues through June to accommodate the Air Resources Board Building construction.
Start: 10/1/2019
End: 12/31/2019
WMWD Project Sterling Pump Station
Where: Pierce/Magnolia/Railroad Tracks
Start: 5/7/2018
End: 03/2020
Royal Palm Blvd. Pipeline Replacement Project
Where: Royal Palm Blvd, Rancho Riverside Mobile Home Park
- Replacing aged 6-inch and 8-inch cement water pipeline
- Construction will include:
- Relocating Rancho Riverside Mobile Home Park water meter to public right-of-way.
- Installation of approximately 500 linear feet total of pipeline
- 7 water services
- 1 fire hydrants
- 3 system connections
- Abandoning approximately 10,070 linear feet of aged pipeline located along an easement
- Trench repaving
- New installations will improve system reliability and improve fire flow capacity.
- Working hours are from 8:00 AM to 4:00 PM, Monday through Friday.
Start: 06/2020
End: 11/2020
Harvey Lynn Substation Expansion Project
Where: 11130 Schuyler Street and intersection with La Sierra Avenue
- Contractor will work from 7:00am to 4:00pm Monday through Friday.
Start: 1/21/2020
End: 8/31/2020
Streetlight Replacement Project
Where: From 14th St. to Mission Inn Ave., between Market St. and Redwood Dr. Larchwood Pl. is also included.
- Installing new streetlight fixtures
- New installations will utilize LED technology for energy efficiency and long service life while maintaining the historical integrity of the existing system.
- Working hours are from 8:00 AM to 4:00 PM, Monday through Friday.
Start: 02/2020
End: 12/2020
Jo Jo Way Water Main Replacement Project
Where: Jo Jo Way and Crest Avenue area
- Construction will include:
- Installation of approximately 1,400 linear feet of 8-inch pipeline
- 17 water services
- 2 fire hydrants
- 5 system connections
- Trench repaving
- New installations will improve the reliability of the water system in the surrounding residential areas.
- Working hours are from 8:00 AM to 4:00 PM, Monday through Friday.
Start: 09/2020
End: 12/2020
Mission Inn Booster Station & Pressure Rezoning Projects
Freeman to Orangecrest Substation - Fiber Installation Project
Where: Orangecrest through Woodcrest Areas
- Installing new fiber optic cable
- Removing existing outdated cable
- New installations will enhance the reliability of the RPU Communications System
- Working hours are from 8:00 AM to 3:00 PM, Monday through Friday.
Start: 12/2019
End: 06/2021
Oleander Court Water Main Replacement and Pressure Rezoning Project
Where: Hawarden Hills Neighborhood
-
Maintenance and repair work of existing water system infrastructure
-
Moving the upper portion of Oleander Court into a higher pressure zone
-
Work includes:
-
Installation of approximately 2,000 feet of pipe
-
7 water service connections
-
Installation of 1 new fire hydrant
-
Trench repaving
-
New installations will improve water system reliability in the area
Start: February 2022
End: May 2022
Magnolia Avenue Techite Pipeline Replacement Project (Harrison St. to Van Buren Blvd.)
Garfield & Overland Water Main Replacement Project (Phase II)
Where: Ramona Neighborhood
- Maintenance and repair work of existing water system infrastructure
- Work includes:
- Installation of approximately 4000 ft of pipe
- 111 water services connections
- Installation of 13 Fire Hydrants
- Trench Repaving
- New installations will improve water system reliability in the area
Start: 08/2021
End: 02/2022
Paving: 05/2022 - 06/2022
Wells and Cypress Avenue Water Main Replacement Project (Phase II)
Magnolia Avenue Techite Pipe Replacement Project
Jackson St. Recycled Water Project
Canyon Crest Cable Replacement (Area 5)
Where: Canyon Crest
- Maintenance and repair work of existing electrical system infrastructure
- Replacing electrical cables and related equipment alongside the thoroughfare and within the City right-of-way
- New installations will enhance electrical system reliability in the area
- Project Map
Start: Summer 2022
End: Fall 2022
McKinley Grade Separation & Waterline Relocation Project
Lincoln Avenue Techite Pipe Replacement Project (Fenwick Place to Saint Lawrence Street)
Brockton Avenue Water Main Replacement Project
Monteel Place Water Main Replacement Project
Where: Ramona Neighborhood
- Maintenance and repair work of existing water system infrastructure
- Work includes:
- Installation of approximately 435 ft of pipe
- 15 water services connections
- Trench Repaving
- New installations will improve water system reliability in the area
- Project Map
Estimated Start: Winter 2023
Estimated Completion: Spring 2023
Toyon Road and Holly Lane Water Main Replacement Project
Where: Ramona Neighborhood
- Maintenance and repair work of existing water system infrastructure
- Work includes:
- Installation of approximately 3500 ft of pipe
- 101 water services connections
- Installation of 9 Fire Hydrants
- Trench Repaving
- New installations will improve water system reliability in the area
- Project Map
Estimated Start: Summer 2022
Estimated Completion: Fall 2022
Paving Completion: Spring 2023
Gibraltar Drive Cable Replacement
Where: Magnolia Center Neighborhood
- Maintenance and repair work of existing electrical system infrastructure
- Replacing electrical cables and related equipment alongside the thoroughfare and within the City right-of-way
- New installations will enhance electrical system reliability in the area
- Project Map
Estimated Start: Fall 2022
Estimated Completion: Winter 2023
Canyon Crest Booster Station Replacement Project
Chestnut Street Water Main Replacement Project
Where: Downtown Neighborhood
- Maintenance and repair work of existing water system infrastructure
- Work includes:
- Construction of approximately 800 linear feet of 8-inch Polyvinyl Chloride (PVCO) pipe
- 17 Water services connections
- Installation of 3 system connections
- Trench Repaving
- Replacement of this pipeline will enhance the water system’s reliability in the area.
- Project Map
Estimated Start: Fall 2023
Estimated Completion: Spring 2024
11th Street Water Main Replacement Project
Where: Eastside Neighborhood
- Maintenance and repair work of existing water system infrastructure
- Work includes:
- Installation of approximately 1250 linear feet of pipe
- 31 water services connections
- Installation of 2 Fire Hydrants
- Trench Repaving
- New installations will improve water system reliability in the area
- Project Map
Estimated Start: Summer 2022
Estimated Completion: Spring 2023
Estimated Paving Completion: January 2024
Bingham and Wolfe Avenue Water Main Replacement Project
Where: La Sierra Neighborhood
- Maintenance and repair work of existing water system infrastructure
- Work includes:
- Installation of approximately 3285 ft of pipe
- 72 water services connections
- Installation of 8 Fire Hydrants
- Trench Repaving
- New installations will improve water system reliability in the area
- Project Map
Estimated Start: Spring 2023
Estimated Paving Completion: December 2023